ASTEC
(Automated Sensing Technologies for Coastal Monitoring)

Work Packages Progress

 

 

WP1 Initial Market Survey

         Completed on schedule

WP2 System Architecture       

        Completed on schedule

WP3 Research Suitable Sensors

        Completed on schedule

WP4 Research protocol stack and routing algorithms

        Completed on schedule

WP5 Modem Beach Trials

        Completed on schedule

WP6 Modem feature development

        Completed on schedule

WP7 Design prototype nodes

        Completed on schedule

WP8 Design protocol stack and routing algorithms

        Completed on schedule

WP9 Develop data acquisition functions

        Completed on schedule

WP10 Manufacture prototype sea bed node

        Completed on February 10th 2010

WP11 Manufacture prototype base node

        Completed on February 10th 2010

WP12 Implement  protocol stack and routing algorithms

        Completed on February 10th 2010

WP13 Implement data acquisition function

        Completed on February 10th 2010

WP14 Analyse and refine hardware and software

        Ongoing

WP15 Underwater testing

        Commenced on February 11th 2010

WP16 Presentation and Publication of Results

        Completed on schedule


 


 


 

News Archives

 

Sea Trial has comenced in Tenby

(11/02/2010) Sea trial began today Thursday February 11th

 

Undersea Trial to Begin

(07/02/2010) Sea trial will now start on Thursday February 11th.

 

Launch of the website

(01/01/2010) SMU has launched the official website for ASTEC, which gives some essential information about the project.

 

Beach trial postponed due to the weather

(14/12/2009) Undersea deployment is cancelled to due to extreme weather warning for 17th December.

 

Completion of WP8

(07/07/2009) Work Package No. 8 has been successfully completed by SMU. The project document version 12 has been delivered.

 

TSB -funded project